Officials are considering lowering Route 1 in Crystal City to ground level after Amazon moves in.
Details remain scant, but officials appear to considering a plan to remove several highway overpasses that span over roads from 12th Street S. to 18th Street S. in favor of at-grade intersections with traffic signals. Currently, the Virginia Department of Transportation (VDOT) is studying the project.
“The study for Route 1 is still in very preliminary stages, where VDOT and Arlington County are looking at feasibility of different concepts, and the best potential balance to accommodate all modes of travel — buses, pedestrians, bicycles, vehicles, etc,” VDOT spokeswoman Jennifer McCord told ARLnow Monday.
When asked, McCord said VDOT did not yet have a cost estimate for the potential project. However, a 2018 Virginia Economic Development Partnership presentation and an entry in the state’s Six-Year Improvement Plan indicate work could cost some $250 million.